A-G’s report on LCS procurement refers to previous govt’s delays, says Khaled Nordin

Defence minister says LCS construction resumed when the unity government came to power

The latest Auditor-General's report found that the Royal Malaysian Navy was behind its procurement schedule, with four out of 18 ships received. – Bernama file pic, July 13, 2024

MACHANG – The Auditor-General’s (A-G) report on the process of procurement of littoral combat ships (LCS), which is said to be at a low level refers to the previous construction status and not the latest.

Defence Minister Datuk Seri Mohamed Khaled Nordin said the construction of the LCS resumed as soon as the unity government took over the administration of Putrajaya, even launching the first LCS ship for testing on May 23.

“The construction of the first LCS so far is according to the schedule and planning set by the government,” he told reporters after officiating the Machang Umno division 2024 delegates meeting at the Bukit Tiu knowledge transformation centre, here last night.

Previously, the media reported an audit review that found that the Royal Malaysian Navy’s (RMN) procurement and target for December 31, 2022 was low, compared to the target of 18 ships set in the 11th Malaysia Plan and the 12th Malaysia Plan.

The procurement total was much lower as only four ships were received or 22.2%, with nine more in the procurement process out of a total of six LCS ships, 10 littoral mission ships (LMS) and two multipurpose support ships (MRSS). – July 13, 2024