KUALA LUMPUR – There will be lane closures and traffic diversions on Jalan Langat, Klang (at Aeon Bukit Tinggi traffic light intersections) to facilitate LRT3 project-related works from April 22 to May 7.
According to the LRT3 project contractor, Setia Utama LRT 3 Sdn Bhd, the closures are from Monday to Sunday, 10pm to 6am.
The road will be closed in following stages:
Stage 1: The left most-lane of Jalan Langat (Klang-bound) and Persiaran Batu Nilam 1 slip road will be closed from April 22-23.
Stage 2: The fast-lane on Jalan Langat (Klang-bound) will be closed from April 23-24.
Stage 3: The fast and middle-lanes on Jalan Langat (Banting-bound) will be closed from April 24-25.
Stage 4: The slow and middle-lanes on Jalan Langat (Banting-bound), slow lane, middle-lane and slip road of Jalan Mahogani, will be closed from April 25-26.
Stage 5: The fast-lane on Jalan Mahogani, (Persiaran Mahogani and Persiaran Batu Nilam-bound) will be closed from April 26-27.
Stage 6: The slip road and slow-lane on Jalan Langat (Banting-bound) and left-most lane of Jalan Mahogani will be closed from April 29-30.
Stage 7: The fast and middle-lanes on Jalan Langat, (Banting-bound) will be closed from May 1-2.
Stage 8: The fast and middle-lanes on Jalan Langat, (Klang-bound) will be closed from May 2-3.
Stage 9: The slow and middle-lanes on Jalan Langat, (Klang-bound) and Persiaran Batu Nilam 1 slip road will be closed from May 3-4.
Stage 10: The fast-lane on Persiaran Batu Nilam 1-both bounds will be closed from May 6-7.
The diversions are implemented following the approval from the Klang Public Works Department.
For public enquiries, contact the LRT3 helpline at 1 800 18 2585 from Monday to Friday (8.30am-5.30pm), excluding public holidays. – April 20, 2024